Preparing for Solar Detach & Reinstall
Preparation for a roof replacement with solar is mostly paperwork and a production baseline. Gather your solar agreement and equipment details, screenshot your monitoring output, confirm access, and clear the driveway. Everything else is our job.
Before the project
-
Locate your solar documents
Installation agreement, equipment list, warranty documents, and whether the system is owned, leased or on a PPA.
-
Screenshot your production
Capture the last 30 days of output from your monitoring app, ideally at the string or panel level. This is your baseline.
-
Confirm monitoring login
Make sure you can access the portal. Homeowners frequently cannot, and it matters at commissioning.
-
Note any existing issues
If a string has been underperforming for months, tell us now so it is on the record before we touch anything.
-
Check for lease or PPA notice requirements
Some agreements require notifying the provider before work on the array.
The week of
- Clear the driveway and move vehicles away from the house
- Remove or secure fragile items on walls and shelves; tear-off vibration knocks things down
- Plan for pets to be somewhere quiet, since the noise is significant
- Take down wind chimes, hanging plants and patio umbrellas near the roofline
- Cover items stored in the attic, since debris falls between decking boards
- Make sure we have access to the electrical panel and inverter location
What to expect day by day
| Day | What happens | Your solar |
|---|---|---|
| Day 1 | System shutdown, panels and racking removed | Production stops |
| Days 1-3 | Tear-off, deck inspection, underlayment, roofing install | Offline |
| Final day | Panels remounted, wiring re-run, system energized | Back online, output verified |
| After | Final photos, warranty registration, monitoring check | Compared against baseline |
Frequently asked questions
- Will I lose power during the project?
- Your home stays on utility power. What stops is solar production, along with any battery charging from solar, for the duration of the work.
- Where are the panels stored while the roof is replaced?
- Typically on site in a protected, staged location, or off site when the property does not allow safe staging. Either way they are labeled by position so the array goes back the way it came off.
- What if a panel is already damaged before you start?
- We photograph the array before removal precisely so pre-existing conditions are documented. If we find damage, we show you before we touch it.
- Do I need to be home?
- Not for the roofing work. We do ask that you be reachable on commissioning day in case we need monitoring portal access to verify production.